The membrane inspected while it is still a membrane and not a finished floor.
Wet area rectification is the most expensive defect category in a new home, because fixing it after tiling means dismantling the room. What we have recorded in Craigieburn is membrane work left simply incomplete in an ensuite, which is the version of this failure that is easiest to catch and cheapest to correct, provided somebody looks before the tiler starts.

Annotated findings from Waterproofing inspections on Craigieburn builds. Client addresses withheld.




1Bored piersAfter boring and cage placement, before any concrete
2Slab pre-pourThe day before the pour, steel and formwork complete
3FrameOnce frame and trusses are up and the roof is on, before lining
4Lock-up (pre-plaster)After roof, cladding and external doors, before plaster
5FixingAfter mouldings, doors and joinery, before the painter
7Pre-handover (PCI)Two to three weeks before your handover dateInstant online pricing, or talk to the booking team on 1300 471 805.
AS 3740 for waterproofing of domestic wet areas, read with the National Construction Code and the ABCB Housing Provisions, alongside your contract and the Guide to Standards and Tolerances.
No. Flood testing is intrusive and belongs to the waterproofer as part of their own process. We inspect visually and by hand, which is what identifies incomplete and badly detailed work.
Often only a few days between the waterproofer finishing and the tiler starting. Book as soon as the waterproofer is scheduled rather than once the work is done.
Usually a damp skirting or a stain on the wall of the adjoining room, a year or two after you move in. By then the remedy is removing tiles and screed and starting again.
It frequently is, and on most Craigieburn builds the two run as a single visit. Where the tiler is close behind, we would rather attend separately and early.
The builder's, as a coordination matter between the waterproofer and the tiler. The report gives them the location and the clause, which is usually enough for it to be redone before tiling.